Whats New

Kitchen area

  • Tandoor ready tiling work , granite topping complete.
  • Wall tiling complete
  • Concealed wiring complete along with switches and plug points
  • Lighting to be fixed by the week
  • Painting of walls to commence this week
  • Drainage pipe laying in progress.
  • Gas bank and charcoal bin fixed
  • Gas pipe lining to be completed

Dining Area

  • Rafter beam work for false ceiling in progress
  • Selected tiles for the toilets
  • Table tops ready… to be polished bases to be PU coated.
  • Side stations / Dummy waiters being readied.

Kitchen civil work expected to be completed by 1st week of July. Expecting the interiors to be readied by 10th. Kitchen Equipments will be delivered hopefully before 10th. Kitchen exhaust to be fixed simultaneously.

Visited the Express Hotelier’s Expo held at the Kanteerva stadium yesterday. Saw some amazing stuff there…wanted to pick them up but held back due to some budgetary constraints. The Waste disposer was certainly very interesting.

John is visiting the site,will finalise some finer aspects of the kitchen design tomorrow.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

  • Blog Stats

  • Other stats

  • Last FM

  • Meta

  • %d bloggers like this: